Work on Brazil's controversial $13 billion Belo Monte [5] hydro-dam has been at a halt since Nov. 11, when workers torched buildings at three work sites of the Monte Belo Construction Consortium (CCBM), hired by parastatal Norte Energia [6] to build the massive complex. The violence broke out after CCBM proposed a seven percent wage hike to the workers in an area where the inflation rate is at 30%. In addition to labor undest, CCBM has also faced physical obstruction by local indigenous peoples. On Oct. 9 a group of protesters—150 natives and local fishermen—interrupted construction, accusing Norte Energia of backtracking on accords signed in June when indigenous people occupied the dam site for three weeks. (AFP [7], Nov. 13; Xingo Vivo [8], Nov. 11) A local court halted construction of the project Aug. 14, finding that indigenous inhabitants had not been consulted, but Brazil's Supreme Federal Tribunal ordered construction to resume two weeks later, citing the project's criticality to "the administrative order, the economic order and the Brazilian energy policy." Brazil's Prosecutor General is to meanwhile investigate the question of whether indigenous peoples had been properly consulted. (The Rio Times [9], Aug. 30)